E & B Paving, faced with material delay and weather, are working hard to wrap the Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1. Over the next few weeks, E & B Paving will be completing the project in accordance with the following UPDATED tentative schedule:
November 4th - November 21st: Pendleton Avenue (from Railroad Crossing to SR 67) Trench, Mill & Install Guardrail and Sign *Expect lane restrictions during construction as well as extended road closure during this time. *Work to be conducted during day hours.
November 22nd: Pendleton Avenue (from Railroad Crossing to SR 67) Paving *Work to be conducted during day hours.
November 28th & 29th: Pendleton Avenue (from Railroad Crossing to SR 67) Permanent Markings & Sign/Barricade Removal *Work to be conducted during day hours.
Please note that all dates are weather dependent. Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires. Further, local residents may experience limited inconvenience the day of the scheduled paving.