Schedule Update - Roadway Resurfacing and Repairs Project
The Town of Pendleton is very excited to begin its Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1. Over the course of the next few months, E & B Paving will be improving several of our local roads according to the following revised tentative schedule:
August 8th – August 12th: Indiana Avenue, Clark Street, Mill Street, Canterbury Street, Asbury Street, Oxford Street, Adams Street & High Street *Work to be conducted during the day hours.
August 15th – August 18th: Adams Street, High Street, Taylor Street, Franklin Street, Mill Street, Water Street & Old SR 132 (excavation/placement) *Work to be conducted during the day hours.
August 18th, 19th & 22nd: Old SR 132 (prep & pave) *Work to be conducted during the day hours.
August 29th – August 31st: State Street (from Main Street to Railroad Viaduct) *Work to be conducted during night hours.
August 31st – October 18th: Pendleton Avenue (from Railroad Crossing to SR 67) *Expect lane restrictions during construction as well as extended road closure roughly three (3) weeks during this time period.
October 19th - October 20th: Water Street, State Street & Pendleton Avenue (install permanent markings)
Please note that all dates are weather dependent. Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires. Further, local residents may experience limited inconvenience the day of the scheduled paving.