Roadway Resurfacing and Repairs Project

The Town of Pendleton is very excited to begin its Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1.  Over the course of the next few months,  E & B Paving will be improving several of our local roads according to the following tentative schedule:

  • August 8th – August 12th:  Indiana Avenue, Clark Street, Mill Street, Taylor Street, Franklin Street, Canterbury Street, Asbury Street, Oxford Street & Water Street  *Work to be conducted during the day hours.            
  • August 15th – August 19th:  Old State Road 132, Adams Street and High Street   *Work to be conducted during the day hours.         
  • August 29th – August 31st:  State Street (from Main Street to Railroad Viaduct)   *Work to be conducted during night hours.                       
  • September 6th – October 22nd:  Pendleton Avenue (from Railroad Crossing to SR 67)   *Expect lane restrictions during construction as well as extended road closure roughly  three (3) weeks during this time period.

Please note that all dates are weather dependent.  Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires.  Further, local residents may experience limited inconvenience the day of the scheduled paving.