Roadway Resurfacing and Repairs Project
Posted on: August 5, 2022 - 1:02pm
The Town of Pendleton is very excited to begin its Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1. Over the course of the next few months, E & B Paving will be improving several of our local roads according to the following tentative schedule:
- August 8th – August 12th: Indiana Avenue, Clark Street, Mill Street, Taylor Street, Franklin Street, Canterbury Street, Asbury Street, Oxford Street & Water Street *Work to be conducted during the day hours.
- August 15th – August 19th: Old State Road 132, Adams Street and High Street *Work to be conducted during the day hours.
- August 29th – August 31st: State Street (from Main Street to Railroad Viaduct) *Work to be conducted during night hours.
- September 6th – October 22nd: Pendleton Avenue (from Railroad Crossing to SR 67) *Expect lane restrictions during construction as well as extended road closure roughly three (3) weeks during this time period.
Please note that all dates are weather dependent. Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires. Further, local residents may experience limited inconvenience the day of the scheduled paving.