Updated Schedule - Roadway Resurfacing and Repairs Project

The Town of Pendleton is very excited that its Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1 is well underway.  Over the course of the next few months, E & B Paving will continue improving several of our local roads according to the following UPDATED tentative schedule:

August 23rd: Water Street (Pave)

August 23rd - August 24th: Old SR 132 (Clean/Prep & Pave) *Work to be conducted during the day hours.

August 26th & August 29th: Franklin, Taylor, Mill. Water and Old SR 132 (Approach work) *Work to be conducted during the day hours.

August 29th - August 31st:  State Street (Mill and Pave from Main Street to Railroad Viaduct)   *Work to be conducted during night hours.                       

September 7th – October 18th:  Pendleton Avenue (from Railroad Crossing to SR 67)   *Expect lane restrictions during construction as well as extended road closure roughly three (3) weeks during this time period. *Work to be conducted during day hours.

October 19th - October 20th: Water Street, State Street & Pendleton Avenue (install permanent markings) *Work to be conducted during day hours.

Please note that all dates are weather dependent.  Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires.  Further, local residents may experience limited inconvenience the day of the scheduled paving.