Updated Schedule - Roadway Resurfacing and Repairs Project
The Town of Pendleton is very excited that its Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1 is well underway. Over the course of the next few months, E & B Paving will continue improving several of our local roads according to the following UPDATED tentative schedule:
August 17th – August 19th: Water Street (Prep/Clean) *Work to be conducted during the day hours.
August 18th – August 19th: Franklin Street, Taylor Street, Mill Road, Water Street, Old 132 (Approach Paving) *Work to be conducted during the day hours.
August 22nd: Old SR 132 (Clean & Prep) *Work to be conducted during the day hours.
August 23rd: Water Street (Pave)
September 7th - August 9th: State Street (Mill and Pave from Main Street to Railroad Viaduct) *Work to be conducted during night hours.
August 31st – October 18th: Pendleton Avenue (from Railroad Crossing to SR 67) *Expect lane restrictions during construction as well as extended road closure roughly three (3) weeks during this time period.
October 19th - October 20th: Water Street, State Street & Pendleton Avenue (install permanent markings)
Please note that all dates are weather dependent. Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires. Further, local residents may experience limited inconvenience the day of the scheduled paving.