Updated Schedule - Roadway Resurfacing and Repairs Project

The Town of Pendleton is very excited that its Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1 is well underway.  Over the course of the next few months,  E & B Paving will continue improving several of our local roads according to the following UPDATED tentative schedule:

August 17th – August 19th:  Water Street (Prep/Clean)  *Work to be conducted during the day hours.           

August 18th – August 19th:  Franklin Street, Taylor Street, Mill Road, Water Street, Old 132 (Approach Paving)   *Work to be conducted during the day hours.         

August 22nd: Old SR 132 (Clean &  Prep) *Work to be conducted during the day hours.

August 23rd: Water Street (Pave)

September 7th - August 9th:  State Street (Mill and Pave from Main Street to Railroad Viaduct)   *Work to be conducted during night hours.                       

August 31st – October 18th:  Pendleton Avenue (from Railroad Crossing to SR 67)   *Expect lane restrictions during construction as well as extended road closure roughly  three (3) weeks during this time period.

October 19th - October 20th: Water Street, State Street & Pendleton Avenue (install permanent markings)

Please note that all dates are weather dependent.  Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires.  Further, local residents may experience limited inconvenience the day of the scheduled paving.