Schedule Update - Roadway Resurfacing and Repairs Project

The Town of Pendleton is very pleased with the progress of its Roadway Resurfacing and Repairs Project as part of the Community Crossings Matching Grant 2022-1.  Over the course of the next few several weeks, E & B Paving will continue improving several of our local roads according to the following UPDATED tentative schedule:

September 19th: Various Roadways (Raise water and sewer to grade) * Work to be conducted during the day hours.

September 19th - 21st: Water Street & Old SR 132 (Install Permanent Markings) *Work to be conducted during the day hours.

September 21st & 22nd: State Street (Install Permanent Markings [centerline] from Main Street to Railroad Viaduct to the east) *Work to be conducted during the day hours.

September 23rd: State Street (Install Permanent Markings [parking spaces] from Main Street to Railroad Viaduct to the east) *Work to be conducted during the day hours. *NO PARKING PERMITTED DURING THIS TIME*                

September 26th – November 4th:  Pendleton Avenue (from Railroad Crossing to SR 67)   *Expect lane restrictions during construction as well as extended road closure roughly three (3) - four (4) weeks during this time period. *Work to be conducted during day hours.

 Please note that all dates are weather dependent.  Contractor E & B Paving will communicate scheduled paving dates and updates to residents along each roadway as the project transpires.  Further, local residents may experience limited inconvenience the day of the scheduled paving.